Throughout the year, the Town of Orangeville undertakes numerous construction and infrastructure projects in order to maintain or improve elements in the Town.
This page will provide updated information on any construction projects that may create disruptions for residents.
Parks and Facilities Projects
Rotary Park - Began August 2024 |
The Rotary Park project, approved by Orangeville Council in June of 2022, is planned over six phases:
Watermain work commenced August 19, 2024. The playground has been removed for the work to proceed and will be replaced by a new structure in 2025. The project is being completed by a private sector contract, RK & Associates Consulting Inc. |
Building Infrastructure Projects
Road Infrastructure Projects
2024 Public Works Summer Repairs Program (Begins July 22) |
||||||||||||||||
The annual summer repairs program focuses on replacing/repairing asphalt, sidewalk, catch basins, manholes, curbs, and more. The schedule below is subject to change.
|
||||||||||||||||
2024 Road Resurfacing Program (Begins July 2, 2024) |
||||||||||||||||
Six roads are slated for the resurfacing treatment between now and the end of September. Anticipated schedule:
Residents are asked to not park on the road if they will be away for an extended period during road resurfacing work. Remember to watch for road workers. |
||||||||||||||||
Cardwell/Townline and Dawson/Broadway Traffic Signals (aligned with projects below) |
||||||||||||||||
Upgrade work to the traffic signals at the intersection of Cardwell Street & Townline and Dawson Road & Broadway is being completed. Both projects will occur during the two projects listed below, according to their location. |
||||||||||||||||
Cardwell Street Reconstruction (Begins Sept. 9, 2024) |
||||||||||||||||
Cardwell Street will undergo street reconstruction by a Private Sector Contractor, impacting the area between Townline and Princess Street. Scope of work:
Here are some things to note:
Residents impacted by the construction will have received a notice from the Town with additional information. If you did not receive this, please send us an email at [email protected]. |
||||||||||||||||
Dawson Road Watermain (Begins mid-fall) |
||||||||||||||||
In late September/Early October a private sector contractor will begin construction of the Dawson Road watermain. Scope of work:
Here are some things to note:
Residents impacted by the construction will have received a notice from the Town with additional information. If you did not receive this, please send us an email at [email protected]. |
||||||||||||||||
Hansen Boulevard Connection |
||||||||||||||||
The alignment of Hansen Boulevard was planned through a municipal class environmental assessment completed through 2006-2007. The western stretch of Hansen Boulevard, between Blind Line and Veteran’s Way, has been constructed in incremental segments over a 10-year period. Segments were completed as surrounding residential subdivision developments were constructed, by the project developers. Segments completed to date (February 2024) include:
The last remaining stretch of Hansen Boulevard falls within future subdivision lands owned by the developer. Why is the work not being completed now?
|
||||||||||||||||
Victoria Street and Ontario Street Reconstruction (Beginning June 3, 2024) |
||||||||||||||||
A private sector contractor hired by the Town of Orangeville will begin the reconstruction of Victoria Street and Ontario Street on June 3. Reconstruction will include, but is not limited to the following: roadway, curbs, sidewalks, streetlighting, concrete curbs and gutters, and storm sewers. Both streets will be closed to traffic for approximately 5 months. Local and emergency traffic will be maintained at all times. Road Closure: Victoria Street and Ontario Street will be closed as of June 3, for approximately 5 months. Local and emergency access will be maintained at all times. Scope of work:
Pre-Construction Elements: There will be some project-related work that will occur ahead of the road work. This includes the installation of tree protection and environmental fencing, locates, surveying, and utility daylighting. A single lane closure will be required ahead of June 3 to complete this work. Resident Impacts:
Frequently asked questions:
|
Projects not run by the Town of Orangeville
The projects in this list are not Town of Orangeville projects but may have a direct impact on residents. Where necessary, the Town will work with the private sector contractors to minimize any negative impacts on its residents and increase safety.
Avalon Care Centre - Started 2023 |
On August 28, 2023 the Ontario government announced a full redevelopment of the Avalon Care Centre, Orangeville's 40-year-old long term care facility. The project will bring more long-term care beds to Orangeville, addressing a critical shortage.
Mitigating traffic disturbances on Preston Drive In response to traffic concerns raised by residents on Preston Drive in 2023, the Town of Orangeville has been working with the project contractor to mitigate negative impacts, safety, or the quality of life for residents. The following measures have been put in place to honour the contractor's commitment, including:
Constructing the building structure:
|