Progress continues in Orangeville with ongoing roadwork, sidewalk work, and more. Here's your construction breakdown for the week of August 19 to 23:
For more information visit orangeville.ca/Construction
- 🚧 Alder Street - Lane restrictions from C-Line to Rayburn Drive: Various concrete work on the North side of the road including sidewalk and curb repairs.
- 🚧 St. Andrew Drive and Meadow Drive: Asphalt milling and base course paving.
- 🚧 Rustic Crescent: Topsoil and sodding.
- 🚧 Victoria Street: Continued work on sewer replacement and service connections.
- 🚧 Dawson Road (Madison Avenue to Lawrence Avenue): Asphalt milling and base course paving.
- 🚧 Third Street (Broadway to First Avenue): Sidewalk and curb repairs/replacements.
- 🚧 C-Line and Centennial Road: Catch basin repair
- 🚧 Broadway (various locations): Sidewalk and catch basin repairs
- 🚧 Broadway and Wellington Street – Construction of a new PXO.
- 🚧 Rotary Park – Watermain replacement.
- 🚧 Broadway – Westbound right lane reduction: Due to construction at the Avalon.
For more information visit orangeville.ca/Construction